Nara Meeting Minutes #4736
Comments
MeetingWednesday 13 September 2023. Status
Milestone ETAs
Risks
|
MeetingMonday 18 September 2023. Attendance
Status
Milestone ETAs
Risks
|
MeetingWednesday 20 September 2023. Attendance
Status
Milestone ETAsNo milestones affected.
Risks
|
MeetingMonday 25 September 2023. Attendance
Status
Milestone ETAsNo milestones affected.
Risks
|
MeetingThursday 28 September 2023. Attendance
Status
Milestone ETAs
JIP:
RisksJIP process is lagging. |
MeetingMonday 2 October 2023. Attendance
Status
Milestone ETAsTech:
JIP:
RisksJIP process is lagging. |
MeetingWednesday 4 October 2023. Attendance
Status
Milestone ETAsTech:
JIP:
RisksJIP process is lagging. |
MeetingMonday 16th October 2023. Attendance
Status
Milestone ETAsTech:
JIP:
RisksJIP process is lagging. |
MeetingWednesday 18th October 2023. Attendance
Status
Milestone ETAsTech
JIP
Upgrade Executed
RisksJIP process is lagging. |
Attendance QA Plan Freeze pallet PR Multisig PR Creator Token Mappings Pioneer Nara branch Nara runtime types |
MeetingWednesday 25th October 2023. AttendanceActive participants were
Status
Milestone ETAsTech
JIP
Upgrade Executed
RisksJIP process is lagging. |
MeetingWednesday 1st November 2023. AttendanceActive participants were
Status
Milestone ETAsTech
JIP
Upgrade Executed
RisksJIP process is lagging. |
MeetingMonday November 6th 2023 Attendance
StatusFreeze pallet proposal status
Deploy of the Nara testnetsThe server setup was started but is not yet completed, scheduled to be completed today (06/11/2023) |
MeetingMonday 13st November 2023. AttendanceActive participants were
Status
Milestone ETAsTech
JIP
Upgrade Executed
RisksJIP process is lagging. |
Meeting was cut short, mokhtar and chaos were not there, not much could be covered, but seems like QA has started and is making progress. |
MM 26.04.23
Status
Migration to Substrate version is pretty muchd one, only weight generation is left. No changes were needed to any palletss in terms of type signatures, storage representations or business logic, it was only renaming a bunch of types for the most.
nara
branch with this work has been created.Migrations
TODO
nara
. CRTs should still be filtered inNara
, but latest implementation should be there. This work can start now. Merge all creator token work intoNara