Meeting 1 (Sept. 25th 2019)

Trottier 5th Flr. Rm.5090 18h00-20h00

  • Project discussion
    • Introduction of members
    • Where to start
  • Detailed look at tutor point of view
  • Discussing functional and nonfunctional requirements
  • First draft of functional and nonfunctional requirements
    • Only the functional requirements

Minutes submitted by Steven Luu


Meeting 2 (Oct. 2nd 2019)

Trottier 4th Flr. Rm.4110 18h00-20h00

  • Finalized requirements
    • Including non-functional requirements
  • Discussion and distribution of the detailing of Use Case Diagrams
    • Only the 5 most important functional requirement
  • First draft of Domain Model
    • Started on piece of paper

Minutes submitted by Mert Gurkan


Meeting 3 (Oct. 6th 2019)

Trottier 5th Flr. 18h00-20h00

  • Finalized domain model
    • Implementation with UML Lab
    • Written by Tian Ci and Mehdi
  • Start of Use Case Diagram
    • Discussion on which actor is the most important
    • Based on our point of view, the tutor is the most important
  • Setup Spring, Heroku, Gradle and Travis
    • Due to technical difficulties Travis could not have been setup

Minutes submitted by Steven Luu


Meeting 4 (Oct. 8th 2019)

Trottier 4th Flr. Rm. 4110 18h00-20h00

  • Assigning each requirement its unique ID based on the decided format
    • FR# for functional requirement
    • NFR# for non-functional requirement
  • Editing detailed specification of use case
    • Added FR1, FR7
    • Edited FR8
  • Tweaking the use case diagram
    • Add missing associations
    • Added constraint on the retrieval of schedule
    • Remove some associations
  • Decide on the correct directory structure of the project
    • Separate folder for Backend, Frontend
    • Separate UML diagram associated code from the generated /src code
  • Discussion on setup from meeting 3
    • Setup of Heroku, Spring and Gradle is completed
    • Still having issues with Travis CI (Trial has ended, and cannot authorize app to our repo)

Meeting 5 (Oct. 10th 2019)

Trottier DPM Lab 17h30-20h00

  • Finishing up the use cases specifications
  • Implementing the persistence layer
    • Issues with getting the database to work

Minutes submitted by Steven Luu last updated by Mehdi Ammar on 2019-10-10 @ 11:33PM