This is a feature request not a issue or defect. Moving this to Discussion page. |
Beta Was this translation helpful? Give feedback.
0 replies
-
I understand your use case, but Roadmapper was intended to be used as a tool to generate high-level roadmap and not project gantt chart. |
Beta Was this translation helpful? Give feedback.
0 replies
-
Ok, I understand, it's normal. However, maybe this option enables a new type of 'use cases' not contemplated so far. In any case, thanks for the development and for the effort. Thx |
Beta Was this translation helpful? Give feedback.
0 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
Currently, the minimum duration of an item is 1 day. If the duration is less, an exception is generated.
Using 1 day as the minimum unit in this type of diagrams, it is impossible to represent events with a lower temporal resolution.
Would it be possible to prepare this project to be able to represent temporal units smaller than 1 day?
Thanks in advance...