If the PEPS-II system is not available for purchase, we could experience a large schedule impact as we identify and procure an alternative system.
Risk Effects:
We have experience with the PEPS-II system from MagAO-X so have software in place that works with the system. We know where we can buy it, and we know the approximate cost. Any new system would involve exploration of capabilities, identification of vendors, and a currently unknown lead time. Once in hand, we would need some time to get experience with the system and to set up for its operations.
Risk Assessment:
Risk Ratings
Likelihood
Consequence
Initial
2
2
Current
Target
0
2
Initial Risk Notes:
Technologies such as the PEPS-II active air leveling system are not guaranteed to stay on the market and are not guaranteed to be in stock when we are ready to make a purchase. The longer we wait to make our purchase, the greater the risk that we will not be able to get what we need on our schedule.
Risk Notes/Updates:
Cost Impacts:
Estimated cost if risk is realized:
Explanation for cost risk:
Risk mitigation list:
Determine the GMagAO-X specific performance needs and get vendor quotes
Investigate whether other air leveling systems can meet our needs
Include the air leveling system in our spares plan
Procure the air leveling system as soon as funding becomes available
The text was updated successfully, but these errors were encountered:
Risk creation date: 8/23/2023
Last Modified: 8/23/2023
Risk type: Schedule
Risk Approach: Mitigate
Risk Owner: Laird Close
Risk Statement:
If the PEPS-II system is not available for purchase, we could experience a large schedule impact as we identify and procure an alternative system.
Risk Effects:
We have experience with the PEPS-II system from MagAO-X so have software in place that works with the system. We know where we can buy it, and we know the approximate cost. Any new system would involve exploration of capabilities, identification of vendors, and a currently unknown lead time. Once in hand, we would need some time to get experience with the system and to set up for its operations.
Risk Assessment:
Initial Risk Notes:
Technologies such as the PEPS-II active air leveling system are not guaranteed to stay on the market and are not guaranteed to be in stock when we are ready to make a purchase. The longer we wait to make our purchase, the greater the risk that we will not be able to get what we need on our schedule.
Risk Notes/Updates:
Cost Impacts:
Estimated cost if risk is realized:
Explanation for cost risk:
Risk mitigation list:
Determine the GMagAO-X specific performance needs and get vendor quotes
Investigate whether other air leveling systems can meet our needs
Include the air leveling system in our spares plan
Procure the air leveling system as soon as funding becomes available