Update docs/system-admin-guide/manage-work-packages/work-package-prog…
Browse files Browse the repository at this point in the history
…ress-tracking/README.md

Co-authored-by: Christophe Bliard <[email protected]>
  • Loading branch information
MayaBerd and cbliard authored Oct 2, 2024
1 parent d743c16 commit 61a7114
Showing 1 changed file with 1 addition and 1 deletion.
Original file line number Diff line number Diff line change
Expand Up @@ -24,7 +24,7 @@ To manage the settings for progress tracking in work packages, navigate to *Adm
>
> - Changing progress calculation mode from work-based to status-based will result in all existing *% Complete* values to be lost and replaced with values associated with each status. Existing values for *Remaining work* may also be recalculated to reflect this change. This action is not reversible.
>
> - Changing progress calculation mode from status-based to work-based will make % Complete a non-editable field whose value is derived from Work and Remaining work. Existing values for % Complete are preserved. If values for Work and Remaining work were not present, they will be required in order to change % Complete.
> - Changing progress calculation mode from status-based to work-based will make the *Complete* field freely editable. If you optionally enter values for *Work* or *Remaining work*, they will also be linked to *% Complete*. Changing *Remaining work* can then update *Complete*.
![Warning message when changing progress calculation mode in OpenProject administration](openproject_system_guide_progress_tracking_settings_warning_message.png)