Expand Up @@ -38,13 +38,13 @@ You can select one of the following relations:

- **Duplicates / Duplicated by** - This option indicates that the work package B duplicates a work package A in one way or another, for example both address the same task. This can be useful if you have the same work package that needs to be a part of a closed and public projects at the same time. The connection in this case is only semantic, the changes you make in work package A will need to be adapted in work package B manually.

**Note**: some changes in statuses will de adjusted automatically for the duplicated work package. Specifically, if the status of a work package A is set to be "closed" (or set to any status that is defined to count as "closed" in the [system settings](../../../system-admin-guide/manage-work-packages/work-package-status/), for example "rejected" often counts as a "closed" status), the status of the work package B will change to "closed". Note that this is direction dependent. Only if the work package A is closed will the work package B be closed as well, not the other way around.
**Note**: some changes in statuses will be adjusted automatically for the duplicated work package. Specifically, if the status of a work package A is set to be "closed" (or set to any status that is defined to count as "closed" in the [system settings](../../../system-admin-guide/manage-work-packages/work-package-status/), for example "rejected" often counts as a "closed" status), the status of the work package B will change to "closed". Note that this is direction dependent. Only if the work package A is closed will the work package B be closed as well, not the other way around.

- **Blocks / Blocked by** - This option defines status change restrictions between two work packages. If you set a work package A to be blocking work package B, the status of work package B cannot be set to closed or resolved until the work package A is closed.

- **Precedes / Follows** - Defines a chronological relation between two work packages. For example, if you set a work package A to precede a work package B, the start date of B has to be at least a day after the finish date of A.
Please note: If work package B is in [manual scheduling mode](../../gantt-chart/scheduling/#manual-scheduling-mode), changing the finish date of work package A will have no effect on work package B.

- **Includes / Part of** - Defines if work package A includes or is part of work package B. This relation type can be used for example when you have a roll-out work package and work packages which should be shown as included without using hierarchical relationships. There is no additional effect.

- **Requires / Required by** - Defines if work package A requires or is required by work package B. There is no additional effect.