This document lays out the development priorities and plans for the Gumtree software version 1.11. The aim of this plan is to provide an overview of works that are committed in the current development iteration cycle. This is a living document and is subject to change based on the project priority.
| Phase | Start | End | Duration | Release | |---|---|---|---|---|---| | Planning | 20/04/2015 | 24/04/2015 | 1w | | | Iteration 0 | 27/04/2015 | 29/05/2015 | 5w | 1.11.0 | | Iteration 1 | 01/06/2015 | 26/06/2015 | 4w | 1.11.1 | | Iteration 2 | 29/06/2015 | 24/07/2015 | 4w | 1.11.2 | | Iteration 3 | 27/07/2015 | 21/08/2015 | 4w | 1.11.3 | | Iteration 4 | 23/08/2015 | 25/09/2015 | 5w | 1.11.4 | | Endgame | 28/09/2015 | 16/10/2015 | 3w | 1.11.5 |
▲ Display buffer queue information in the status page.
▲ Plan and try solutions for communications between Gumtree server and Client.
▼ Access instrument control log from server.
Add automatic logging feature.
▼ Add drag-n-drop SICS component feature.
Provide time estimation for TCL scripts.
Publish time estimation on status servers of all instruments.
▼ Dynamically adapt the time estimation.
▼ Reload Hipadaba model when reconnecting to SICS.
▼ Provide system test framework that includes Gumtree, SICS and Histogram server.
▼ Develop a standard for the communication between Gumtree and SICS.
▲ Provide generic MSW framework.
▲ Implement and deploy Quokka MSW. V1.11.1
Implement and deploy Kookaburra MSW.
Implement and deploy Bilby MSW.
▲ Provide generic electronic notebook framework.
▲ Implement electronic notebook for Quokka. V1.11.1
▲ Build a Gumtree workbench that support Python debugging.
Review and update Python interface of SICS module.
Update fitting interface.
▲ Migrate Gumtree documents to other content management server
Instrument model feature.
White paper for Gumtree 2.0.