Introduction

This document lays out the development priorities and plans for the Gumtree software version 1.9. The aim of this plan is to provide an overview of works that are committed in the current development iteration cycle. This is a living document and is subject to change based on the project priority.

Release Schedule

Phase Start End Duration Release Planning 01/07/2013 05/07/2013  1w   Iteration 0 08/07/2013 06/09/2013 9w 1.9.0 Iteration 1 09/09/2013 18/10/2013 6w 1.9.1 Iteration 2 21/10/2013 15/11/2013 4w 1.9.2 Iteration 3 18/11/2013 06/12/2013 3w 1.9.3 Iteration 4 09/12/2013 14/02/2014 10w 1.9.4 Endgame 17/02/2014 21/03/2014 5w 1.9.5

Plan Items

Category Plan Items Server Side
  • Automatically launch or stop Gumtree server with sync of SICS (tick)
  • Migrate all servers to a single host box (tick)
Plotting
  • Improve plotting quality (tick)
  • Provide more plotting features (tick)
SICS Proxy
  • Evaluate Scala language 
  • Evaluate Vertex project  (tick)
  • Revise interface/message between SICS and Gumtree
Data Reduction
  • Quokka data reduction support
  • Evaluate porting DAVE lib to Gumtree (tick)
Scripting
  • Upgrade scripting UI support (tick)
  • Improve Python interface for SICS support
Quokka
  • Finalise the product (tick)
  • Time estimation project
Kowari
  • Reduction in Python script (tick)
Kookaburra
  • Multi-sample workflow
Taipan
  • Static window for live data support
  • Dial widget for detector counts (tick)
  • Diffscan & meshscan support (tick)
Platform
  • Remove unnecessary dependencies
Future Plan
  • White paper for Gumtree 2.0
 